Balfour Beatty Vinci (BBV), working in partnership with HS2 Ltd, will be carrying out utility surveys on the M6 junction 4, the A446 Stonebridge Road and the M6 J4 roundabout between 1st and 8th March.

In each case, work will take place between 9pm and 5am the following morning:

1 -2 March

Utility surveys on the northbound carriageway of the A446 between Chester Road and junction 4 of the M6, including the Junction itself. Lane closures to be installed between 9pm on Tuesday 1 March until 5am the following morning.  The works also require the complete closure of the northbound slip road that connects the A446 with the A452 at the Northway Island

Click map for full details

2 – 4 March

Utility surveys on the M6 junction 4 and the A446. BBV will fully close the Northbound slip road leading to the junction and close a Southbound lane on the A446. Northbound traffic wishing to exit the M6 at junction 4 will be diverted south via the M42 then on to the A45 at Junction 6 of the M42, then north via the A452 at the Stonebridge Island.

Click map for full details

4 – 5 March

Utility surveys on the A446 and junction 4 of the M6.  BBV will close a lane on the southbound carriageway of the A446 near junction 4 of the M6, including the southbound entrances and exits of the Junction.

Click map for full details

7 – 8 March

Utility surveys on the M6 junction 4 roundabout.  BBV will close a lane on the roundabout at junction 4 of the M6 – including the approaches from the A446. 