Balfour Beatty VINCI (BBV), working in partnership with HS2 Ltd, will be carrying out traffic management in the following locations during December and January 2022:
Coleshill Heath Road Works – 20-23 December and 10-21 January
BBV had previously sent out a notification outlining trial excavation works to be complete on Coleshill Heath Road. Works initially were set to take place from Monday 20 December until Wednesday 22 December. As a result of the reduced working window, (brought in to ease traffic flows and minimise disruption) they will need to continue works for longer than expected.
Prior to Christmas, BBV will extend works from Wednesday 22 December until Thursday 23 December. After Christmas they will continue works from Monday 10 January until Friday 21 January. They will have traffic management throughout both these sets of work.
There may be Saturday work dependant on the programmes progress. Working hours for Saturdays are 8.00am until 1.00pm and 9.30am until 4.00pm on weekdays. Pedestrian access will be maintained at all times and the bus stop has been relocated outside the lane closure.
Chester Road Works – 5-6 January
On Wednesday 5 January and Thursday 6 January 2022, BBV will carry out ground investigation works in land adjacent to the A452 Chester Road. To carry out these works safely, they will need to install a lane closure on the southbound carriageway of the A452 Chester Road, near the Stonebridge island. This will allow access and exit to the land for their works. The lane closure will be operational from 09.30am to 3.30pm.